Planned Power, Data Interruptions: July 13, 14, and 25

The Buffalo State College campus will experience temporary interruptions to its electrical service this month. Service interruptions lasting about 15 minutes will occur in the buildings listed below.

Campus Internet services will resume after power has been restored. Building occupants need not take any special action with computers, refrigerators, or similar equipment because the planned interruptions will be brief.

Dates and locations for the planned service interruptions are as follows:

Wednesday, July 13  |  6:00–7:00 a.m.

  • Bacon Hall
  • Bengal Hall
  • Bishop Hall
  • Buckham Hall
  • Burchfield Penney Art Center
  • Campus House
  • Houston Gym
  • Ketchum Hall
  • Neumann Hall
  • Rockwell Hall
  • Savage Building
  • Sports Arena

-------------------------------------

Thursday, July 14  |  6:00–7:00 a.m.

  • Campbell Student Union
  • Cleveland Hall
  • Moore Complex
  • Perry Hall
  • Science and Mathematics Complex
  • Student Apartment Complex
  • Towers 1, 2, 3, and 4

-------------------------------------

Monday, July 25  |  12:01–1:00 a.m.

  • Central Heating Plant
  • Clinton Center
  • Elms Hall (Classroom Building)
  • Technology Building
  • Twin Rise
  • Weigel Wellness Center

The July 25 shutdown will interrupt power to the campus data center. Staff members in the IT Department will do their best to restore network connections for the workday.

Thank you for your patience and understanding as the campus conducts preventive maintenance in the main electrical substation. Questions about this work may be addressed to vpfm@buffalostate.edu.

Submitted by: Jill Powell